BUILDING RENO UPDATE!

A TIMELINE OF RENOS

  1. Mid-June: Medwin Mechanical removes old AC units from gym roof and begins interior work to replace HVAC system

  2. End-June: Caswell Roofing begins replacing gym roof

  3. June 29: fire on roof

  4. July: insurance claims, initial cleaning, dehumidifying, deep cleaning, duct cleaning, flooring ripped out

  5. August 1-2: roofing work finished

  6. Final mitigation steps to come: painting, replace flooring, reinstall gym kitchen cabinets

  7. Next up: HVAC installation on newly finished roof


When work began on the roof in mid-June, we had no idea what would be in store for us. At that time, Medwin Mechanical began work to replace the HVAC system by removing the old AC units from the gym roof. They also began interior work needed for this replacement. Later in the month, Caswell Roofing began replacing the gym roof. Unfortunately, a fire began on the roof on June 29th and the fire department was called, which required the firefighters to douse the area with water. This incident resulted in damage that needed to be remediated. The month of July was busy with regard to building projects; insurance claims, initial cleaning, dehumidifying, deep cleaning, duct cleaning, and the flooring being ripped out. As of August 2nd, the roofing work is finished. Praise the Lord! The next steps in the gym are painting, replacing flooring, and reinstalling the gym kitchen cabinets. The final element in all of this will be the HVAC installation on the newly finished roof. This will be such a blessing and we look forward to this completed work and the ability to gather in our gym once again.